Work has started yesterday. Should be a slab going down by the end of next week!!!
Following the building process of our Mediterranean 2 split level design by Montgomery Homes, on a sloping block.
Saturday, August 29, 2009
Tuesday, August 25, 2009
Saturday, August 15, 2009
Thursday, August 13, 2009
Phonecall from site superviser
Got a phonecall today from site superviser saying he was out at the block. Surveyers will be there in the next few days and excavators might be there on around the 23rd August. The safety/security fence will be put up in the next few days also.
Friday, August 7, 2009
Construction to Commence
Received a letter today from Montgomery Homes saying construction to commence on 27th August.
Thursday, August 6, 2009
Internal Colurs and Selections
External Colours and Selections
Some plans and site plans
Wednesday, August 5, 2009
Block cleared today
The building area of the block has been cleared today. Was done by Newcastle Earth Moving newcastleearthmoving.com for $1500. I think a vey good price. included stump removal and all. Not the clearest photos as I only had the mobile phone camera.
Tuesday, August 4, 2009
Photos of Block
Here are some pics of the block prior to being cleared. It slopes down to the front of the block and a bit from right to left. heaps of trees and undergrowth to b cleared. Will be nice to have trees around once the house is built tho.
Contracts Signed
Today we have been to Montgomery Homes office and signed the tender and contracts. The fire protection level went down from level 3 that we had in the tender to level 1 after review by council and the rural fire service so that has taken $3000 off the tender price.
The block should be cleared some time this week as well.....then we just wait for the excavations and building to start.
The block should be cleared some time this week as well.....then we just wait for the excavations and building to start.